Guidance on temporary closure of construction sites
Risk management
The following provides guidance on how to manage a construction site shutdown in order to reduce the risks and impact of any issues during a temporary closure of the works
Temporary closure - pre-planning considerations
- Carry out a risk assessment of the site
- Consider the legal and contractual implications of a temporary closure of the site
- Create a close down plan which specifically details critical areas on the site
- Establish a list of key contacts and detail responsibilities
Temporary closure - when demobilisation commences
- Document the progress made on site to date
- Ensure emergency services access plans and provisions remain in place
- Remove waste from the site or secure covered and lockable containers
- Remove or secure scaffolding to prevent access
- Inspect current temporary support works
- Establish additional temporary support works for part built structures
- Back fill or cover over excavations and ensure dewatering systems are working
- Lock anti-climb hatches on tower cranes and note the expiry date of the certificate of thorough examination
- Retain essential electrical power supplies but drain down water systems and shut off water and gas supplies
- Remove materials and plant from site back to a secure depot or secure within lockable containers and buildings
- Check the site fencing and make any necessary repairs
- Establish site security during the closure period (whether staffed or remote monitoring)
- Record contact information for key personnel and establish responsibility for site access
Construction insurance solutions and inspection services
We have a comprehensive range of construction insurance products covering all aspects of projects across the UK and Ireland.
Our engineering inspection services also help customers to maintain workplace equipment safety, optimise the efficiency of a vast range of plant and equipment, and comply with applicable health and safety legislation.